Contract Award Notice
Date of publication: November 7, 2022
Pursuant to ITB 45.2, this is to notify that the Department of Roads, Development Cooperation Implementation Division, SRCTIP has awarded the following contract invited through Notice No. SRCTIP/8/078-79 as per following:
Contract No: SRCTIP-DOR-W-NNM-ICB-3
Description of Works: Improvement of Road and Bridges of Malekhu-Muglin Section (Km. 43+542 to 82+403) of Prithvi Highway
Selection Method: Request for Bids – Works (After Prequalification)
S.No. |
Name of Bidders |
Bid price (read out) |
Evaluated Bid price (excluding VAT and PS) |
Remarks |
1. |
Kalika-Swachhanda JV |
6,117,857,124.64 incl VAT |
5,224,949,762.22 |
|
2. |
YYRBC-SAMANANTAR JV |
4,603,955,763.86 incl PS & excl VAT |
4,574,468,867.60 |
|
3. |
China First Highway Engineering Co. Ltd |
5,695,552,074.86 incl VAT & PS |
4,851,815,995.45 |
|
4. |
Kumar-Sichuan-K.S. JV |
5,852,456,639.36 incl VAT & PS |
4,990,473,572.35 |
|
5. |
Shandong Luqiao Group Co., Ltd. |
6,324,384,004.43 incl VAT & PS |
5,408,304,428.30 |
|
6. |
GYC-TUNDI JV |
5,830,245,515.08 incl VAT & PS |
4,871,593,455.56 |
|
7. |
Longjian-Ashish JV |
5,013,519,560.64 incl VAT & PS |
4,248,247,398.80 |
|
8. |
Sharma-ZICG JV |
4,805,974,912.64 incl VAT & PS |
4,069,500,367.22 |
|
9. |
Simplex-Rautaha-Apex JV |
5,381,720,537.30 incl VAT & PS |
4,528,348,081.35 |
|
Successful Bidder:
S.N. |
Contract No. |
Description of Works |
Name of the Bidder |
Contract Amount (With 13% VAT) |
Contract Duration |
1. |
SRCTIP-DOR-W-NNM-ICB-3 |
Improvement of Road and Bridges of Malekhu-Muglin Section (Km. 43+542 to 82+403) of Prithvi Highway |
M/S Sharma-ZICG Joint Venture |
NPR 4,805,974,912.64 (including VAT and PS) |
3 years Construction and 5 Years PBMC (Total 8 years) |