कार्य क्षेत्र
1. Project Road
The project road is located in central region of Nepal. The project road starts at outskirts of Narayanghat Town and ends at Mugling Town of Chitwan District. The total length of project road is 33.253 km which has been divided into three Contract Packages namely ICB-1 (10.45 Km), ICB-2 (10.69 Km) and ICB-3 (12.113 Km).
The project road is being constructed under Nepal India Regional Trade and Transport Project (NIRTTP) scheme of the Government of Nepal.
Narayanghat - Mugling Road is part of Asian Highway connecting Kathmandu to Indian boarder and is a major trade route. The whole road alignment is following the left bank of the Trishuli River. The road gradually ascends from Narayanghat (Chainage 0+000. elev. 200m) to Ramnagar (Chainage 5+500, elev. 250m) along Northern face of the hilly terrain. From Ramnagar the road runs along Trishuli River and the alignment ascends towards Mugling (Chainage 35+677, Elev. 285 m.).
2. Silent Features of the Project
- Name of Project Road : Narayanghat - Mugling Road
- Project Road Length : 33.253 Km
- Location
a) Geographical Region : Central Development Region of Nepal
b) Zone : Narayani Zone
c) District : Chitwan
- Class of Road : National Highway H05
(To be upgraded to Asian Highway Standards)
- Right of Way : 30 m
- Cross Section
a) Bituminous Carriageway : 2 Lane (7.00 m)
b) Road Width : 11.00 m from Km 2+400 to Km 16+000
9.00 m from Km 16+000 to Km 35+653
- Shoulder : 2 m on both sides from Km 2+400 to Km 16+000
:1 m on both sides Km 16+000 to Km 35+653
- Pavement Composition : Bituminous Concrete = 40 mm
Dense Bituminous Macadam = 120 mm
Crushed Stone Base = 250 mm
Granular Sub-Base = 200 mm
Capping Layer = 300 mm (If required)
2. Project Data
Some important data pertaining to all three Contract Packages are given below:
Sl. No. |
Descriptions |
Contract Packages |
Remarks |
||
---|---|---|---|---|---|
ICB-1 |
ICB-2 |
ICB-3 |
|||
1 |
Name of the Road |
Narayanghat - Mugling Road |
|
||
2 |
Road Length (Km) |
10.450 (Km 2+400 – 12+850) |
10.690 (Km 12+850 – 23+540) |
12.113 (Km 23+540 – 35+653) |
Total = 33.253 Km |
3 |
Contract No. |
NIRTTP-DOR-W-ICB-1 |
NIRTTP-DOR-W-ICB-2 |
NIRTTP-DOR-W-ICB-3 |
|
4 |
Contract Price including VAT(NRs) |
606,063,992.62 |
976,681,244.84 |
1,304,268,972.90 |
Total = 2,887,014,210.36 |
5 |
Funding Agency |
The World Bank (IDA Credit No. 5273-NEP) |
|
||
6 |
Engineer |
Intercontinental Consultants and Technocrats Pvt. Ltd, New Delhi, India in Joint Venture with Soosung Engineering Co. Ltd, Korea and in association with Full Bright Consultancy (Pvt.) Ltd, Kathmandu, Nepal |
|
||
7 |
Contractors |
BLA - SCC JV |
Woodhill - Lama JV |
Supreme - Rautaha JV |
|
8 |
Date of Agreement |
02 April 2015 |
31 March 2015 |
23 March 2015 |
|
9 |
Commencement Date |
20 April 2015 |
24 April 2015 |
20 April 2015 |
|
10 |
Construction Period |
24 months from Start Date |
24 months from Start Date |
24 months from Start Date |
|
Extension of Time (EOT-1) |
128 Days |
127 Days |
136 Days |
|
|
Extension of Time (EOT-2) |
92 Days |
92 Days |
109 Days |
|
|
11 |
Extension of Time (EOT-3) |
81 Days |
|
63 Days |
|
12 |
Original Completion Date |
19 April 2017 |
23 April 2017 |
19 April 2017 |
|
13 |
Revised Completion Date |
14 Feb., 2018 |
28 November 2017 |
20 Feb., 2018 |
|
14 |
Duration of DNP |
365 Days |
365 Days |
365 Days |
As per Contract |
15 |
Engineering Design by |
MMM Group Ltd in JV with SAI Consulting Engineers (P) Ltd, in association with ITECO Nepal and TMS Nepal. |
|
Abbreviations used:
NRs = Nepali Rupees, DOR = Department of Roads, VAT = Value Added Tax,
DNP = Defects Notification Period, ICB = International Competitive Bidding,
IPC = Interim Payment Certificate, Km = Kilometer, NEP= Nepal
- BLA - SCC JV = Joint Venture of BLA Projects Pvt. Ltd, India and
Shrestha Construction Co. Pvt. Ltd, Nepal.
- Woodhill - Lama JV = Joint Venture of Woodhill Infrastructure Limited, India and Lama Construction Company Pvt. Ltd., Nepal.
- Supreme-Rautaha JV = Joint Venture of Supreme Infrastructure India Ltd., India and Rautaha Construction Pvt. Ltd., Nepal.
3. Project Progress Status
(As on 20 July 2017)
Project progress status pertaining to all three Contract Packages are given below:
Sl. No.
Contract Number
Planned (%)
Achieved (%)
Total Slippage (%)
Time Elapsed (%)
1
NIRTTP-DOR-ICB-1
68.94
50.80
18.14
79.73
2
NIRTTP-DOR-ICB-2
89.55
58.57
30.98
86.20
3
NIRTTP-DOR-ICB-3
63.29
50.04
13.25
79.27
4. Major work Completed
(As on 20 July 2017)
S. N.
Contract Location and Length
Contract No.
Earthwork
(Back Cutting)
Earthwork (Grade Cutting)
Side Drain
Sub Grade
Sub Base
Base
DBM
1
Km 2+400 to 12+850
Length= 10.450 KM
NIRTTP – DOR – ICB – 1
10.25 KM
(Remaining= 0.20 KM)
1.00 KM
1.0 KM
5.20 KM
5.00 KM
4.80 KM
4.00 KM
2
Km 12+850 to 23+540
Length = 10.690 KM
NIRTTP – DOR – ICB – 2
10.20 KM (Remaining= 0.49 KM)
5.20 KM
4.15 KM
5.20 KM
3.20 KM
2.00 KM
0.80 KM
3
Km 23+540 to 35+653
Length = 12.113 KM
NIRTTP – DOR – ICB – 3
11.50 KM (Remaining= 0.61 KM)
3.50 KM
3.00 KM
3.40 KM
3.00 KM
1.70 KM
0.20 KM
Note: Retaining Structures in all the contracts are 95% completed.
5. Project Expenditure
1. Total Project Cost (Current and Capital) --------------- Nrs. 3.62 Billion
(पुँजीगत र चालु गरि आयोजनाको क्रियाकलापको कुल बजेट--------३ अर्ब ६२ करोड)
2. Total Expenditure upto FY 2072/073-------------------- Nrs. 1.0252 Billion
(आ.व. २०७२/७३ सम्मको कुल खर्च---------------------------------१ अर्ब २ करोड ५२ लाख)
3. Total Budget of FY 2073/074-------------------------------- Nrs. 1.5622 Billion
(आ.व. २०७३/७४ को कुल बजेट------------------------------------- १ अर्ब ५६ करोड २२ लाख)
4. Total Expenditure of FY 2073/074--------------------------- Nrs.581.1 Million
(आ.व. २०७३/७४ को कुल खर्च ----------------------------------------- ५८ करोड ११ लाख)
5. Total Expenditure to date ---------------------------------------- Nrs. 1.6063 Billion
(आयोजनाको हालसम्मको खर्च----------------------------------------- १ अर्ब ६० करोड ६३ लाख
Expenditure of FY 2073/074
(आ.व. २०७३/७४ को खर्च)
IDA Loan ----------------------------------- Nrs 0.553 Billion
बैदेशिक ऋण ------------------------------------ रु. 553,146,573.67
GoN --------------------------------------------- Nrs 27.95 million
नेपाल सरकार--------------------------------------- रु. 27950309.14
Note: The above cost doesn’t include the cost of consultancy service
नोट: यसमा परामर्शदाताको खर्च समाबेश गरिएको छैन