कार्य क्षेत्र

1.    Project Road

The project road is located in central region of Nepal. The project road starts at outskirts of Narayanghat Town and ends at Mugling Town of Chitwan District. The total length of project road is 33.253 km which has been divided into three Contract Packages namely ICB-1 (10.45 Km), ICB-2 (10.69 Km) and ICB-3 (12.113 Km).

The project road is being constructed under Nepal India Regional Trade and Transport Project (NIRTTP) scheme of the Government of Nepal.

Narayanghat - Mugling Road is part of Asian Highway connecting Kathmandu to Indian boarder and is a major trade route. The whole road alignment is following the left bank of the Trishuli River. The road gradually ascends from Narayanghat (Chainage 0+000. elev. 200m) to Ramnagar (Chainage 5+500, elev. 250m) along Northern face of the hilly terrain. From Ramnagar the road runs along Trishuli River and the alignment ascends towards Mugling (Chainage 35+677, Elev. 285 m.).

2.    Silent Features of the Project

  • Name of Project Road             :  Narayanghat - Mugling Road
  • Project Road Length                :  33.253 Km
  • Location

                      a) Geographical Region           :  Central Development Region of Nepal

                      b) Zone                                    :  Narayani Zone

                      c) District                                 :  Chitwan

  • Class of Road                          :  National Highway H05

                                                        (To be upgraded to Asian Highway Standards)

  • Right of Way                           :  30 m
  • Cross Section

                    a) Bituminous Carriageway      :  2 Lane (7.00 m)

                    b) Road Width                         :  11.00 m from Km 2+400 to Km 16+000     

                                                                         9.00 m from Km 16+000 to Km 35+653

  • Shoulder                                  :  2 m on both sides from Km 2+400 to Km 16+000 

                                                            :1 m on both sides Km 16+000 to Km 35+653

  • Pavement Composition           :   Bituminous Concrete      = 40 mm

                                                         Dense Bituminous Macadam     = 120 mm

                                                         Crushed Stone Base                    = 250 mm

                                                         Granular Sub-Base                     = 200 mm  

                                                         Capping Layer                           = 300 mm (If required)

2.    Project Data

Some important data pertaining to all three Contract Packages are given below:

Sl. No.

Descriptions

Contract Packages

Remarks

ICB-1

ICB-2

ICB-3

1

Name of the Road

Narayanghat - Mugling Road

 

2

Road Length (Km)

10.450

(Km 2+400 – 12+850)

10.690

(Km 12+850 – 23+540)

12.113

(Km 23+540 – 35+653)

Total = 33.253 Km

3

Contract No.

NIRTTP-DOR-W-ICB-1

NIRTTP-DOR-W-ICB-2

NIRTTP-DOR-W-ICB-3

 

4

Contract Price including VAT(NRs)

606,063,992.62

976,681,244.84

1,304,268,972.90

Total =

2,887,014,210.36

5

Funding Agency

The World Bank (IDA Credit No. 5273-NEP)

 

6

Engineer

Intercontinental Consultants and Technocrats Pvt. Ltd, New Delhi, India

in Joint Venture with Soosung Engineering Co. Ltd, Korea

and in association with Full Bright Consultancy (Pvt.) Ltd, Kathmandu, Nepal

 

7

Contractors

BLA - SCC JV

Woodhill - Lama JV

Supreme - Rautaha JV

 

8

Date of Agreement

02 April 2015

31 March 2015

23 March 2015

 

9

Commencement Date

20 April 2015

24 April 2015

20 April 2015

 

 

 

10

Construction Period

24 months from Start Date

24 months from Start Date

24 months from Start Date

 

Extension of Time (EOT-1)

128 Days

127 Days

136 Days

 

Extension of Time (EOT-2)

92 Days

92 Days

109 Days

 

11

Extension of Time (EOT-3)

81 Days

 

63 Days

 

12

Original Completion Date

19 April 2017

23 April 2017

19 April 2017

 

13

Revised Completion Date

14 Feb., 2018

28 November 2017

20 Feb., 2018

 

14

Duration of DNP

365 Days

365 Days

365 Days

As per Contract

15

Engineering Design by

MMM Group Ltd in JV with SAI Consulting Engineers (P) Ltd, in association with ITECO Nepal and TMS Nepal.

 

 

 

Abbreviations used:    

NRs = Nepali Rupees, DOR = Department of Roads, VAT = Value Added Tax,

DNP = Defects Notification Period, ICB = International Competitive Bidding,

IPC = Interim Payment Certificate, Km = Kilometer, NEP= Nepal

  • BLA - SCC JV        =     Joint Venture of BLA Projects Pvt. Ltd, India and

                                               Shrestha Construction Co. Pvt. Ltd, Nepal.    

  • Woodhill - Lama JV    = Joint Venture of Woodhill Infrastructure Limited, India and Lama Construction Company Pvt. Ltd., Nepal.
  • Supreme-Rautaha JV =   Joint Venture of Supreme Infrastructure India Ltd., India and           Rautaha Construction Pvt. Ltd., Nepal.

    3.    Project Progress Status

    (As on 20 July 2017)

    Project progress status pertaining to all three Contract Packages are given below:

     

    Sl. No.

    Contract Number

    Planned (%)

    Achieved (%)

    Total Slippage (%)

    Time Elapsed (%)

    1

    NIRTTP-DOR-ICB-1

    68.94

    50.80

    18.14

    79.73

    2

    NIRTTP-DOR-ICB-2

    89.55

    58.57

    30.98

    86.20

    3

    NIRTTP-DOR-ICB-3

    63.29

    50.04

    13.25

    79.27

     

    4.    Major work Completed

    (As on 20 July 2017)

     

    S. N.

    Contract Location and Length

    Contract No.

     

    Earthwork

    (Back Cutting)

    Earthwork (Grade Cutting)

    Side Drain

    Sub Grade

    Sub Base

     

    Base

     

    DBM

    1

    Km 2+400 to 12+850

    Length= 10.450 KM

    NIRTTP – DOR – ICB – 1

     

    10.25 KM

    (Remaining= 0.20 KM)

    1.00 KM

    1.0 KM

    5.20 KM

    5.00 KM

    4.80 KM

    4.00 KM

    2

    Km 12+850 to 23+540

    Length = 10.690 KM

    NIRTTP – DOR – ICB – 2

     

    10.20 KM (Remaining= 0.49 KM)

    5.20 KM

    4.15 KM

    5.20 KM

    3.20 KM

    2.00 KM

    0.80 KM

    3

    Km 23+540 to 35+653

    Length = 12.113 KM

    NIRTTP – DOR – ICB – 3

     

    11.50 KM (Remaining= 0.61 KM)

    3.50 KM

    3.00 KM

    3.40 KM

    3.00 KM

    1.70 KM

    0.20 KM

     

    Note: Retaining Structures in all the contracts are 95% completed.

     

     

     

     

    5.    Project Expenditure

    1. Total Project Cost (Current and Capital) --------------- Nrs. 3.62 Billion

    (पुँजीगत र चालु गरि आयोजनाको क्रियाकलापको कुल बजेट--------३ अर्ब ६२ करोड)

     

    2. Total Expenditure upto FY 2072/073-------------------- Nrs. 1.0252 Billion

    (आ.. २०७२/७३ सम्मको कुल खर्च---------------------------------१ अर्ब २ करोड ५२ लाख)

     

    3. Total Budget of FY 2073/074-------------------------------- Nrs. 1.5622 Billion

    (आ.. २०७३/७४ को कुल बजेट------------------------------------- १ अर्ब ५६ करोड २२ लाख)       

     

    4. Total Expenditure of FY 2073/074--------------------------- Nrs.581.1 Million

    (आ.. २०७३/७४ को कुल खर्च ----------------------------------------- ५८ करोड ११ लाख)

     

    5. Total Expenditure to date ---------------------------------------- Nrs. 1.6063 Billion

    (आयोजनाको हालसम्मको खर्च-----------------------------------------   १ अर्ब ६० करोड ६३ लाख

     

    Expenditure of FY 2073/074

    (आ.. २०७३/७४ को खर्च)

    IDA Loan ----------------------------------- Nrs 0.553 Billion          

    बैदेशिक ऋण ------------------------------------ रु. 553,146,573.67

    GoN --------------------------------------------- Nrs 27.95 million

    नेपाल सरकार---------------------------------------   रु. 27950309.14

     

    Note: The above cost doesn’t include the cost of consultancy service

    नोट: यसमा परामर्शदाताको खर्च समाबेश गरिएको छैन     